The Data Center Next Door Now Has a Price Tag
Duke's new data-center tariff sets 75% minimum billing and 15-year terms. What the Nov 16 NCUC order means for NC landowners — and what to check first.
Published: 2026-11-26. Author: James A. Person Jr. (JP). Human-reviewed; figures carry a named source and date.
On November 16, 2026, the North Carolina Utilities Commission wrote the terms under which a data center can move into Duke Energy territory — and, for the first time, put a binding price on what it costs everyone else when one does.
This is not a story about servers. It is a story about land, records, and who pays when a 50-megawatt neighbor arrives on a rural road.
If you own land in the Piedmont, the Sandhills, or anywhere a transmission line runs past a cheap parcel, this order touches you — even if no data center is proposed near you yet. The terms are now written down. The counties are already reacting. And the property record you keep — or don't keep — is what decides whether you are ready when the conversation reaches your road.
What the Commission actually ordered
The NCUC's November 16 orders approved new rates effective January 1, 2027, for Duke Energy Carolinas and Duke Energy Progress, and created a new data-center tariff, Schedule DC, for loads of 50 megawatts and up. The headline terms:
- 15-year minimum contracts for data centers at 100 megawatts and above; 10-year minimums at 50 megawatts and up.
- Minimum billing at 75% of contracted demand — a data center pays for at least three-quarters of the power it contracted for, whether it uses it or not.
- Upfront payments for dedicated facilities, plus financial and security requirements for transmission upgrades.
- A stranded-generation charge that runs to the 35th year of service — if a data center leaves early, the cost of the generation built for it does not simply vanish onto other customers.
- Refunds with interest if planned infrastructure upgrades run late.
The Commission rejected the large-load tariff Duke had settled in October with the Public Staff, Amazon, Google, Meta, Microsoft, and the Defense Department, and wrote its own Schedule DC instead. Duke says it is still assessing that portion of the order.
The residential side of the same orders: Duke Energy Carolinas rates rise an average of 4.8% a year over two years, Duke Energy Progress 4.7% a year — roughly 9.5% and 9.3% cumulatively. The combined revenue increase is $834 million over two years ($496 million for Carolinas, $338 million for Progress), at a 9.8% return on equity. For a typical household using 1,000 kilowatt-hours a month, that means about $6.53 more a month on a Carolinas bill from January 1, 2027, then another $4.66 from January 1, 2028; on a Progress bill, about $9.62, then $5.89. The two utilities combine into one company on January 1, 2027, with rates staying separate and blending gradually, and the orders include $20 million in new shareholder-funded customer-assistance funding.
One analyst estimate puts the scale of the stranded-generation charge in concrete terms: AIxEnergy, writing November 25, calculated that for a 300-megawatt campus on a 15-year term, the charge is worth about $72 million in present value. That is their calculation, not the Commission's number — and the order leaves two methods to be determined later: how transmission-upgrade costs are assigned by customer benefit, and how exactly the stranded-generation charge is calculated. No per-data-center dollar figure is final yet.
The scale behind the tariff is large. The Inference reported November 17 that Duke has 7.8 gigawatts of a 15.4-gigawatt company-wide large-load pipeline under signed agreements, with 5.2 gigawatts of data centers under construction and drawing power from late 2027.
The pushback is already in North Carolina counties
The tariff is only half the story. The other half is what counties are doing about the buildings themselves — and it reached North Carolina this month.
Chowan County voted 3–2 for a one-year data-center pause through November 2027. That is a county commission in eastern North Carolina deciding, in a public vote, to stop and think before the next proposal lands.
It is not an isolated vote. Wayne County, Michigan, issued a stop-work order on November 20 against Google's Project Cannoli data center — no permits, obstructed drains, sedimentation. Vantage withdrew its 860,000-square-foot, 500-megawatt Trident campus in Aurora, Colorado, on November 25, the same day the council approved a moratorium through September 2027. In Texas, Senator Perry filed a statewide data-center pause bill on November 20. Digital Realty, meanwhile, filed a 156-megawatt plan in Rolling Meadows — the build-out has not stopped; it is being contested, county by county.
Read those together and the pattern is plain: the question is no longer whether data centers come to North Carolina. The question is on whose terms, with whose record, and who pays when one leaves.
The use case: a Moore County landowner hears a rumor
The scenario below is illustrative — a labeled scenario, not a client story. It is built from the public facts above and from the kind of land work RHS does every week.
A landowner outside Southern Pines owns 40 acres her family has held since the 1970s. The land is timbered on the back half, open pasture in front, with a county road on one side and a transmission corridor two parcels over. In the third week of November, a neighbor mentions at the feed store that a developer has been asking about options on the parcel across the road — "something with computers, big power."
She has no proposal in hand. She has a rumor, a road, and a transmission line. Here is what the record-first approach looks like, step by step.
Step 1: Pull your own parcel record before anyone else frames it
Before she calls anyone, she pulls the record that already exists: the county parcel card, the deed and easement history, the zoning designation, and the flood and soils information for her own land. The point is not to become a surveyor. The point is to know, in her own hands, what her land is on paper — because the first document a developer's representative will ever show her is their version of that same record, and she should be able to spot the difference.
This is the same discipline behind our Moore County land check — the kind of parcel record to pull first is at rhsaisolutions.com/land/moore/golf-lot-check/ — and it is the first move in any property intelligence work: your record first, their proposal second.
Step 2: Map the three things that decide a data-center site
A data-center developer needs three things, and all three are visible in public records:
- Power. Is there a substation or transmission corridor within reach, and who owns the easement? The Schedule DC tariff exists precisely because these loads are so large that the grid has to be rebuilt for them — and the 75% minimum billing rule exists because a developer that contracts for 100 megawatts and uses 40 should not leave the other 60 on its neighbors' bills.
- Water. Cooling needs water, and the county's water picture matters. Greensboro, an hour north, has been under Stage 2 mandatory water restrictions since November 3, with combined lake storage around 56% as of November 12 and a Stage 3 trigger at 51.3%. A landowner who knows her county's water position asks a sharper question than one who doesn't.
- Entitlement. What does the county's zoning actually allow on the parcel in question, and has the county said anything about data centers at all? Chowan County's 3–2 pause vote is the clearest possible proof that this question is live in North Carolina right now.
Step 3: Write down what you see, dated, before the trucks arrive
If a proposal does come, the landowner's best asset is a dated record made before the construction traffic starts: photos of the road, the ditch line, the drainage path across her land, the tree line, the condition of the shared driveway. Dates matter. The November 25–26 storm that just crossed central North Carolina — 2 to 5 inches forecast, with 5 to 8 inches possible locally — is exactly the kind of event that shows where water goes on a parcel, and a photo taken this week is worth ten taken after grading begins.
This is the same lesson from our November 24 post on the adjuster's AI file: someone else is already building a file on your property. The question is whether you have one too.
Step 4: Know what the tariff does — and does not — do for you
Schedule DC protects ratepayers as a class: the 75% minimum billing and the stranded-generation charge to year 35 are designed so a departing data center cannot dump its costs on everyone else. What it does not do is decide whether a data center belongs next to your land. That decision sits with the county commission, the planning board, and the record you bring to the hearing.
A landowner who walks into that hearing with a dated, photo-backed record of her own property — drainage, access, easements, current use — is not arguing from memory. She is arguing from evidence. That is the whole of property intelligence: the record first, the argument second.
Where RHS AI Solutions fits — and where it doesn't
RHS AI Solutions is the AI division of Right Hand Services by JP, a real field business in Candor, North Carolina, operating since 2008. We build property intelligence the way field people think about it: observations first, structure second, automation last.
- AI Property Reports (starting ranges $75–$750, portfolio packs $50–$100 — always negotiable) organize property observations, maintenance concerns, and supporting information into a clear, human-reviewed starting point for decisions.
- Environmental Risk Reports (starting ranges $200–$1,500) extend that same discipline to drainage, vegetation, and flood exposure — the exact questions a data-center proposal raises for the land around it.
- Digital Twin Mapping (starting ranges $1,000–$10,000) builds a portfolio-level record for owners with more than one parcel to protect.
And here is what we say plainly on our own website, because it belongs in every post like this one: we are not a certified software vendor, we do not provide legal, engineering, or inspection services, and all work is screening-level and requires human review. The AI organizes information and automates repeatable steps. People decide. We do not give legal advice on zoning, easements, or utility tariffs, and nothing in this post is legal advice — it is a description of public records and a public order, with the sources below so you can read them yourself.
That boundary is not a weakness in the offer. In a month when a county commission voted 3–2 to pause and think, a screening-level record that a real person reviewed is exactly the tool a landowner needs before anyone asks her to sign anything.
The practical next step
If you own land in the Piedmont or the Sandhills — or anywhere a transmission corridor runs — do these three things before the next proposal reaches your road:
- Pull your parcel record now. Deed, easements, zoning, flood and soils information. Know what your land is on paper before someone else tells you.
- Photograph your drainage this week. The storm that just crossed the state showed you where the water goes. A dated photo taken now is evidence; a memory is not.
- Get a second set of eyes on the record. That is what our AI Opportunity Audit is built for: Express $750 (async, one week), Standard $1,500 (with walkthrough call), Deep $2,500 (multi-site/portfolio) — with the audit fee credited toward implementation if you build with us within 60 days.
Start with the record, not the rumor. You can request a sample through rhsaisolutions.com, call (317) 395-3309, or email righthandservicesbyjp@gmail.com. We'll prepare a sample on our own property first, so you can judge the work before your property is ever involved.
The data center next door now has a price tag — 75% minimum billing, 15-year terms, a charge that runs to year 35. The counties are voting. The record you keep is the only part of this story you control, and the time to build it is before the proposal arrives, not after.
Sources
- Duke Energy, "North Carolina regulators approve more cost-effective path to strengthen reliability and power the state's future" (Nov 16, 2026): https://news.duke-energy.com/releases/north-carolina-regulators-approve-more-cost-effective-path-to-strengthen-reliability-and-power-the-states-future
- GCN, "North Carolina Duke Energy rate hikes" (Nov 2026): https://gcn.com/north-carolina-duke-energy-rate-hikes/23418/
- The Inference, "North Carolina regulators approve Duke's $834 million rate rise and impose 15-year data-center terms" (Nov 17, 2026): https://theinference.org/article/north-carolina-regulators-approve-duke-s-834-million-rate-rise-and-impose-15-year-data-center-terms
- AIxEnergy, "What a data center owes when it leaves" (Nov 25, 2026): https://www.aixenergy.io/what-a-data-center-owes-when-it-leaves/
- Baxtel, "North Carolina sets 75% minimum billing for Duke Energy data centers" (Nov 2026): https://baxtel.com/news/north-carolina-sets-75-minimum-billing-for-duke-energy-data-centers
- Commercial-private monitor, Runs 133–134 (Nov 25–26, 2026) — Chowan County 3–2 data-center pause; Wayne County MI stop-work order on Google Project Cannoli; Vantage Trident withdrawal; Texas pause bill: goal hidden_files/commercial-private-monitor/log.md
- NWS Raleigh storm forecast, Nov 25–26, 2026: https://forecast.weather.gov/showsigwx.php?warnzone=NCZ041&warncounty=NCC183&firewxzone=NCZ041&local_place1=2%20Miles%20E%20Raleigh%20NC&product1=Hazardous+Weather+Outlook&lat=35.8222&lon=-78.6239
From the RHS Gumroad storefront
Field guides and planners from RHS AI Solutions / Right Hand Services by JP — https://righthandjp.gumroad.com
Southern Hedge Fill-In Field Guide (FREE) • Fall Garden Cleanup (FREE) • Yard Drainage Diagnosis ($15) • Southern Irrigation Winterization ($15) • Southern Winter Soil Testing ($15) • Southern Pest Control ($7) • Winter Broad-leaf Weed Control – Dormant Southern Turf ($25) • Property Management Planner ($12) • 2026 Spray Season Profit Tracker ($27) • RHS Signature Field Guide: The Southern Art of Landscape Design ($15) • Regenerative Landscaping Field Guide ($9.99) • Contractor Paperwork Pack ($27) — plus the Noble / Big Butch children's storybooks.
RHS AI Solutions — a division of Right Hand Services by JP, Candor / Troy, NC. Practical AI. Real-world purpose.
Right Hand Services by JP · 514 Brutonville Rd, Candor NC 27229 · 317-395-3309 · righthandservicesbyjp@gmail.com